When parties to a contract agree in advance on the amount of compensation payable if one of them breaches, they are using what Indian law calls Section 74 compensation - more commonly known internationally as a "liquidated damages" clause. Understanding when such a clause is enforceable, when courts will reduce the agreed amount, and when it functions as an unenforceable penalty is essential for anyone drafting or relying on these clauses in India. Related internal resource: "contract review checklist before signing" (/resources/contract-review-checklist-before-signing)
The Statutory Framework: Section 74, Indian Contract Act 1872
Section 74 provides: "When a contract has been broken, if a sum is named in the contract as the amount to be paid in case of such breach, or if the contract contains any other stipulation by way of penalty, the party complaining of the breach is entitled, whether or not actual damage or loss is proved to have been caused thereby, to receive from the party who has broken the contract reasonable compensation not exceeding the amount so named or, as the case may be, the penalty stipulated for."
The Key Elements Of Section 74:
The court awards reasonable compensation - not necessarily the full contracted amount The court will not award more than the amount named in the contract The court can and will award less if the full amount would be unreasonable in the circumstances Crucially: the claimant does not need to prove exact loss - but must prove some loss was suffered THE CRITICAL EVOLUTION: ONGC v SAW PIPES (2003) In Oil and Natural Gas Corporation Ltd v. Saw Pipes Ltd (2003), the Supreme Court of India made a landmark interpretation of Section 74. The Court held that: Section 74 does not distinguish between a "genuine pre-estimate of loss" (liquidated damages) and a "penalty" in the way that English law does. Under Indian law, both are governed by Section 74. The court's role is to award reasonable compensation - which may equal the contractual amount if that amount is a genuine estimate of the likely loss. The party claiming the Section 74 amount does not need to prove the exact quantum of loss, but must show that some loss was suffered. Courts can reduce the contractual amount if it is in the nature of a penalty disproportionate to the actual loss or likely loss. THE REFINEMENT: KAILASH NATH ASSOCIATES v DDA (2015) The Supreme Court in Kailash Nath Associates v. Delhi Development Authority (2015) revisited Section 74 and significantly tightened the rule on proof of loss: Where a party suffers no loss whatsoever from the breach, they cannot recover the contractual amount under Section 74 - even if the amount is labelled as liquidated damages. Proof of some actual loss is required. The claimant cannot recover merely because the contract says they can. However, where loss is proved but exact quantification is difficult, the court will use the contractual amount as a reasonable estimate.
Practical Implications Of Ongc And Kailash Nath Together
Scenario 1: You have a liquidated damages clause. The breach occurred. You suffered loss but it is hard to quantify exactly. Result: Section 74 / ONGC allows you to recover the contracted amount as a reasonable estimate, without proving every rupee of loss. Scenario 2: You have a liquidated damages clause. The breach occurred. You suffered no loss at all (the market moved in your favour, the delay caused no actual damage, you found an alternative supplier at the same price). Result: Kailash Nath prevents recovery of the contracted amount - you recover nothing, or nominal damages only. Scenario 3: You have a penalty clause (an amount grossly disproportionate to any genuine estimate of loss). Breach occurred. Loss occurred. Result: ONGC allows the court to award reasonable compensation up to the contracted amount - but the court will not enforce the full penalty if it is grossly disproportionate. You recover reasonable compensation, not the penalty sum.
To Withstand Challenge Under Section 74 And To Be Enforced By An Indian Court:
The amount must represent a genuine pre-estimate of loss: The drafting history matters. If you can show that the contracted amount was calculated by reference to likely costs (replacement costs, loss of business, regulatory penalties), it is far more likely to be enforced than an arbitrary round number. Include the calculation methodology in the recitals or a schedule: "The parties agree that the LD amount of Rs.X per week represents a genuine estimate of the losses that would be incurred by the Client in the event of delay, including re-deployment of internal resources (Rs.A per week), cost of temporary alternatives (Rs.B per week), and regulatory penalties for late compliance (estimated at Rs.C)." Cap the total LD: Total liquidated damages should be capped as a percentage of the contract value (often 5-15%). An uncapped LD clause that could theoretically result in liquidated damages exceeding the contract value will face enforceability challenges. Specify the trigger precisely: When does the LD obligation begin? When does it stop? Is it per day of delay, per unit below specification, or per occurrence of breach? Consider a bonus/penalty structure: For construction and delivery contracts, a symmetric structure (bonus for early completion, LD for late completion) is more equitable and signals that the LD is a genuine estimate rather than a penalty.
Common Mistakes In Liquidated Damages Clauses
No connection between the LD amount and any identifiable loss: The number appears arbitrary - courts are less likely to enforce it in full. LD continues to accrue after the breach is remedied: If the contractor fixes the defect or makes delivery, LD should stop accruing on the date of remedy. LD clause that applies regardless of whether the delay was caused by the client: If the client caused or contributed to the delay, the LD clause cannot be invoked. LD clause as the sole remedy: Some contracts state that LD is the sole remedy for delay, excluding all other claims. This may inadvertently prevent the innocent party from claiming for losses that exceed the LD cap. Consider whether this is the intended position. Force majeure and LD: The contract should specify that LD does not accrue during a force majeure period. Related internal resource: force majeure clause in Indian contracts
How Inamdar Legal Can Help
We draft liquidated damages clauses for construction, supply, technology, and service contracts - advising on LD rates, caps, and structures that are commercially appropriate and legally defensible under Section 74 and the ONGC v. Saw Pipes line of cases. Inamdar Legal is a Surat-based legal practice advising businesses, MSMEs, startups, and individuals across Gujarat and India. We combine deep knowledge of Indian law with practical, plain-English advice that helps clients act with confidence. Contact our Surat office for a consultation. We respond the same day for straightforward matters. DISCLAIMER: This article is for general informational purposes only and does not constitute legal advice. Laws and procedures may change. Please consult a qualified lawyer for advice specific to your situation.
When to obtain a review
A review is especially useful when…
- — You are about to sign, send, rely on or respond to this document.
- — The draft was copied from an old template or another state.
- — There is money, property, business control, statutory deadline or reputation risk involved.
- — You need Surat/Gujarat-specific drafting, review or negotiation support.
Legal information notice
This article is general legal information for India and Gujarat. It is not a substitute for advice on your specific facts, documents, limitation period, stamp duty position or court strategy.

